Card type

Earned value management

28 cards
  1. 01

    A status report shows CPI = 1.10 and SPI = 0.90. What is the project's condition?

    • A

      Under budget and ahead of schedule

    • B

      Over budget and behind schedule

    • C

      Under budget and behind schedule

    • D

      Over budget and ahead of schedule

  2. 02

    A 10-month project has a budget at completion (BAC) of $100,000, spread evenly over the months. At the end of month 4, what is the planned value (PV)?

    • A

      It cannot be known without the actual cost

    • B

      $100,000

    • C

      $40,000

    • D

      $60,000

  3. 03

    A project's BAC is $200,000. The team reports that 50% of the total work is complete. What is the earned value (EV)?

    • A

      It depends on how much has been spent

    • B

      It depends on how much was planned by now

    • C

      $200,000

    • D

      $100,000

  4. 04

    EV is $80,000 and AC is $100,000. What is the cost performance index (CPI), and what does it mean?

    • A

      −$20,000: the project is under budget

    • B

      1.25: the project is 25% under budget

    • C

      0.80: every dollar spent has earned only 80 cents of work

    • D

      0.80: the project is 20% behind schedule

  5. 05

    EV is $80,000 and PV is $90,000. What is the schedule performance index (SPI)?

    • A

      0.89: behind schedule

    • B

      0.89: over budget

    • C

      1.00: on schedule

    • D

      1.13: ahead of schedule

  6. 06

    A project has EV of $150,000 and AC of $170,000. What is the cost variance, and is that good or bad?

    • A

      −$20,000: over budget

    • B

      +$20,000: ahead of schedule

    • C

      +$20,000: under budget

    • D

      −$20,000: behind schedule

  7. 07

    EV is $150,000 and PV is $130,000. What is the schedule variance?

    • A

      −$20,000: behind schedule

    • B

      It cannot be expressed in dollars

    • C

      +$20,000: ahead of schedule

    • D

      +$20,000: under budget

  8. 08

    BAC is $500,000 and the CPI so far is 0.80. Assuming the cost performance to date continues, what is the estimate at completion (EAC)?

    • A

      $500,000

    • B

      $625,000

    • C

      $600,000

    • D

      $400,000

  9. 09

    BAC is $500,000, EV is $100,000 and AC is $120,000. The overrun so far was caused by a one-off problem that will not recur. What is the EAC?

    • A

      $500,000

    • B

      $520,000

    • C

      $625,000

    • D

      $600,000

  10. 10

    BAC is $500,000, EV is $100,000, AC is $120,000, CPI is 0.80 and SPI is 0.90. Management believes both the cost and schedule trends will continue. What is the EAC?

    • A

      $520,000

    • B

      $625,000

    • C

      $675,556

    • D

      $555,556

  11. 11

    A project's EAC is $625,000 and its AC to date is $100,000. What is the estimate to complete (ETC)?

    • A

      $400,000

    • B

      $725,000

    • C

      $525,000

    • D

      $625,000

  12. 12

    BAC is $500,000 and EAC is $625,000. What is the variance at completion (VAC)?

    • A

      −$125,000: the project will finish over budget

    • B

      +$125,000: the project will finish under budget

    • C

      −$125,000: the project will finish late

    • D

      $0: the budget is fixed

  13. 13

    BAC is $500,000, EV is $100,000 and AC is $120,000. What CPI must the team achieve on the remaining work to finish exactly on the original budget?

    • A

      1.05

    • B

      0.83

    • C

      1.25

    • D

      0.80

  14. 14

    Same project (BAC $500,000, EV $100,000, AC $120,000), but management has approved a new EAC of $600,000. What is the TCPI against that EAC?

    • A

      1.20

    • B

      0.83

    • C

      0.80

    • D

      1.05

  15. 15

    A project is in its final week, three months later than planned. EV = $490,000, PV = $500,000, BAC = $500,000. SPI is 0.98. Why is SPI so close to 1.0 on a badly late project?

    • A

      Because PV reaches BAC at the planned end date and EV reaches BAC at the actual end, so SPI always converges to 1.0 as a project finishes

    • B

      Because the report used the wrong PV

    • C

      Because the project has caught up on schedule

    • D

      Because SPI measures cost, not schedule

  16. 16

    Planned value (PV) is the budgeted cost of which work?

  17. 17

    Earned value (EV) is the budgeted cost of which work?

  18. 18

    What is the formula for cost variance (CV)?

  19. 19

    What is the formula for schedule variance (SV)?

  20. 20

    What is the formula for the cost performance index (CPI)?

  21. 21

    What is the formula for the schedule performance index (SPI)?

  22. 22

    Which estimate at completion (EAC) formula applies when the cost performance so far is expected to continue?

  23. 23

    Which estimate at completion (EAC) formula applies when the variance so far was a one-off and the remaining work will go to plan?

  24. 24

    Which estimate at completion (EAC) formula applies when both the cost and the schedule performance so far are expected to persist?

  25. 25

    Which estimate at completion (EAC) formula applies when the original estimate is no longer credible?

  26. 26

    What is the formula for the estimate to complete (ETC), given an EAC?

  27. 27

    What is the formula for the variance at completion (VAC)?

  28. 28

    What is the to-complete performance index (TCPI) needed to finish within the original budget (BAC)?

Critical path method

4 cards
  1. 29

    A small network has four activities. A (3 days) starts the project. B (4 days) and C (6 days) both follow A. D (2 days) follows both B and C and ends the project.

    What is the critical path and the project duration?

    • A

      A–C–D, 11 days

    • B

      A–B–D, 9 days

    • C

      A–C–D, 9 days

    • D

      A–B–C–D, 15 days

  2. 30

    A schedule has two paths: the critical path of 30 days and a second path of 28 days. The project manager shortens a critical activity by 4 days. What is the new project duration?

    • A

      28 days: the second path is now critical

    • B

      24 days

    • C

      30 days: nothing changes

    • D

      26 days

  3. 31

    A project must finish 3 days earlier. Crash costs per day: activity A (critical) $500, activity B (critical) $300, activity C (not critical) $100. Which activity should be crashed first?

    • A

      B: the cheapest activity on the critical path

    • B

      A: the most expensive, so it has the most slack

    • C

      C: the cheapest activity overall

    • D

      All three equally

  4. 32

    Two ways to compress a schedule: overlapping design and construction so they run partly in parallel, or paying overtime to finish design faster. What are these techniques, and what does each cost you?

    • A

      Fast tracking (adds risk of rework) and crashing (adds cost)

    • B

      Fast tracking (adds cost) and crashing (adds scope)

    • C

      Resource levelling and resource smoothing

    • D

      Crashing (adds risk) and fast tracking (adds cost)

Float (project management)

3 cards
  1. 33

    A small network has four activities. A (3 days) starts the project. B (4 days) and C (6 days) both follow A. D (2 days) follows both B and C and ends the project.

    How much total float does activity B have?

    • A

      0 days

    • B

      2 days

    • C

      4 days

    • D

      6 days

  2. 34

    Activity X has total float of 5 days and free float of 0 days. What does that combination tell the project manager?

    • A

      The data is inconsistent: free float cannot be less than total float

    • B

      X can slip 5 days without affecting any other activity

    • C

      X can slip 5 days without delaying the project, but any slip at all delays its immediate successor

    • D

      X is on the critical path

  3. 35

    What is the formula for an activity's total float?

Program evaluation and review technique

5 cards
  1. 36

    An activity's optimistic estimate is 4 days, most likely 8 days and pessimistic 18 days. What is its PERT (beta distribution) expected duration?

    • A

      10 days

    • B

      9 days

    • C

      11 days

    • D

      8 days

  2. 37

    Optimistic 4 days, most likely 8, pessimistic 18. What is the PERT standard deviation of the activity's duration?

    • A

      5.44 days

    • B

      1.17 days

    • C

      2.33 days

    • D

      7 days

  3. 38

    An activity's PERT estimate is 10 days with a standard deviation of 2 days. Assuming a normal distribution, within what range will the duration fall about 95% of the time?

    • A

      8 to 12 days

    • B

      9 to 11 days

    • C

      6 to 14 days

    • D

      4 to 16 days

  4. 39

    A critical path has two activities. One has a standard deviation of 2 days and the other 1.5 days. What is the standard deviation of the path's total duration?

    • A

      6.25 days

    • B

      3.5 days

    • C

      1.75 days

    • D

      2.5 days

  5. 40

    What is the PERT (beta) expected duration for optimistic, most likely and pessimistic estimates $O$, $M$ and $P$?

Three-point estimation

1 card
  1. 41

    Same estimates: optimistic 4, most likely 8, pessimistic 18 days. What is the triangular expected duration?

    • A

      9 days

    • B

      7.3 days

    • C

      8 days

    • D

      10 days

Dependency (project management)

2 cards
  1. 42

    Activity "Pour foundation" finishes on day 10. "Erect frame" has a finish-to-start dependency on it with a 3-day lag for the concrete to cure. When can "Erect frame" start?

    • A

      Day 10

    • B

      Day 11

    • C

      Day 7

    • D

      Day 13

  2. 43

    "Concrete must cure before the frame goes up" and "We prefer to finish the whole design before starting any code" are both dependencies. How does the PMBOK classify them?

    • A

      Both are mandatory

    • B

      The first is mandatory (hard logic); the second is discretionary (soft logic)

    • C

      The first is discretionary; the second is mandatory

    • D

      The first is external; the second is internal

Resource leveling

1 card
  1. 44

    A scheduler adjusts start dates so that no engineer is booked for more than 40 hours a week, and accepts that the project will finish later. Which technique is this?

    • A

      Resource smoothing

    • B

      Fast tracking

    • C

      Crashing

    • D

      Resource levelling

Complete graph

2 cards
  1. 45

    A project team grows to 10 people (including the project manager). How many potential communication channels are there?

    • A

      10

    • B

      45

    • C

      90

    • D

      100

  2. 46

    A team of 6 gains 2 members. How many new communication channels does that create?

    • A

      15

    • B

      13

    • C

      2

    • D

      28

Expected value

1 card
  1. 47

    A risk has a 30% probability of costing $50,000 and an opportunity has a 20% probability of saving $20,000. What is the combined expected monetary value?

    • A

      −$15,000

    • B

      +$4,000

    • C

      −$30,000

    • D

      −$11,000

Decision tree

1 card
  1. 48

    Build in-house: costs $100,000; 60% chance of a $300,000 payoff, 40% chance of a $50,000 payoff. Buy a product: costs $150,000 for a certain $230,000 payoff. Which option has the higher EMV?

    • A

      Build, with an EMV of $100,000 versus $80,000

    • B

      Buy, with an EMV of $80,000 versus $100,000

    • C

      Build, with an EMV of $200,000

    • D

      Buy, because it has no risk

Cost contingency

1 card
  1. 49

    A project's cost baseline is $1,000,000 and includes $80,000 set aside for identified risks. Separately, the sponsor holds $50,000 for unforeseen work. What are these two amounts called, and which can the project manager spend without going back to the sponsor?

    • A

      Both are contingency reserve

    • B

      Both are management reserve

    • C

      Contingency reserve (inside the baseline, PM's authority) and management reserve (outside the baseline, needs sponsor approval)

    • D

      Management reserve (inside the baseline) and contingency reserve (outside it)

Point of total assumption

1 card
  1. 50

    A fixed-price incentive fee contract has a target cost of $100,000, a target profit of $10,000, a ceiling price of $120,000 and a buyer/seller share ratio of 80/20. What is the point of total assumption (PTA)?

    • A

      $120,000

    • B

      $110,000

    • C

      $125,000

    • D

      $112,500

Cost-plus contract

1 card
  1. 51

    A cost-plus-incentive-fee contract has a target cost of $100,000, a target fee of $10,000 and a buyer/seller share ratio of 80/20. Actual cost comes in at $90,000. How much does the buyer pay in total?

    • A

      $110,000

    • B

      $98,000

    • C

      $100,000

    • D

      $102,000

Payback period

1 card
  1. 52

    A project costs $100,000 and will generate net savings of $30,000 per year. What is its payback period?

    • A

      2.5 years

    • B

      3 years

    • C

      4 years

    • D

      3.33 years

Benefit–cost ratio

1 card
  1. 53

    A project's benefits are valued at $300,000 and its costs at $200,000. What is its benefit–cost ratio, and what does a ratio above 1 mean?

    • A

      $100,000: the project is profitable

    • B

      0.67: costs exceed benefits

    • C

      1.5: benefits exceed costs

    • D

      1.5: costs exceed benefits

Opportunity cost

1 card
  1. 54

    An organisation can fund only one of two projects: A has an NPV of $50,000 and B has an NPV of $70,000. It picks B. What is the opportunity cost of that choice?

    • A

      $20,000

    • B

      $50,000

    • C

      $70,000

    • D

      $120,000

Sunk cost

1 card
  1. 55

    A project has already spent $400,000. Finishing it will cost another $200,000 and deliver $150,000 of benefit. Cancelling it now costs nothing further. What should the project manager recommend?

    • A

      Cancel: the remaining $200,000 buys only $150,000 of benefit, and the $400,000 is sunk

    • B

      Continue: the project is two-thirds funded

    • C

      Continue: $550,000 of benefit is needed to recover the investment

    • D

      Continue: cancelling would waste the $400,000

Quality costs

1 card
  1. 56

    Which of these are costs of conformance in the cost-of-quality model?

    • A

      Rework, scrap and warranty claims

    • B

      Only the cost of the final product audit

    • C

      Training, process documentation and inspections

    • D

      Lost customers and liability lawsuits

Control chart

1 card
  1. 57

    On a control chart, seven consecutive measurements fall on the same side of the mean, though all are inside the control limits. What should the project manager conclude?

    • A

      The process is in control because nothing breached the limits

    • B

      The process is out of control: a non-random pattern (rule of seven) signals an assignable cause

    • C

      Nothing: only points outside the limits matter

    • D

      The specification limits need widening

Pareto chart

1 card
  1. 58

    A defect analysis shows that three of twenty defect types account for 80% of all defects. What tool displays this, and what is the principle behind it?

    • A

      A histogram of random variation

    • B

      A control chart, based on the rule of seven

    • C

      A Pareto chart, based on the 80/20 rule: focus on the vital few causes

    • D

      A scatter diagram, showing correlation

Scrum (software development)

1 card
  1. 59

    An agile team completed 20, 24 and 22 story points in its last three sprints. 110 points of work remain in the backlog. Roughly how many more sprints are needed?

    • A

      It cannot be estimated

    • B

      5 sprints

    • C

      4 sprints

    • D

      6 sprints

Agile software development

1 card
  1. 60

    Requirements are well understood and unlikely to change, the technology is familiar, and regulators require the full design to be approved before construction. Which life cycle fits best?

    • A

      Hybrid, because every project needs both

    • B

      Predictive (plan-driven), because the requirements are stable and up-front approval is mandated

    • C

      Agile, because it is always faster

    • D

      Agile, because requirements always change

End of deck · 60 cards

Save